- AMIX SALVAGE ARCTIC TUK BARGE
-
September 30, 2005
Arctic Tuk Crane Instalation Completed. The 600 ton lifting capacity crane securely intalled on the deck of the barge.
-
August 1, 2005
Fabricated panels and supporting brakets installation completed.
-
July 1, 2005
The fabricated sections delivered to Amix Salvage.
-
April 4, 2005
Work has started in Meridian Marine's workshop to fabricate sections
required for the construction of the "New Stern Sectionn" of
the Arctic Tuk.
|